PORT ASSETS

LLC " Novotrans Active"

In 2018, the company “Novotrans Asset” has started realization of the investment project LUGAPORT to create a modern port infrastructure in the development of 4, 5, 6-th stage of the Complex of General cargo in the commercial seaport of Ust-Luga.

The projected terminal is located in the Leningrad region, Kingisepp district, Vistino rural settlement, sea port “Ust-Luga”. The advantageous geographical position of the sea port and the possibility of receiving vessels with large displacement will contribute to positive changes in the aspect of increasing the export and import potential of Russia.

Implementation of project LUGAPORT will complete the integrated development of the last three

areas of the water area within the boundaries of the port of Ust-Luga. The constructed terminal will be able to enter the list of the most powerful and modern terminals and give a powerful impetus to the development of railway infrastructure of the North-Western region, Central Russia and Siberia.

45+

billion rubles

investment in the project

TERM OF REALIZATION INVESTMENT PROJECT:

2018-2022

February 2018 –
December 2022

(for bulk cargo)

2023

December

(for other goods)

COMPLETED STEPS
August
2019

Construction of the LUGAPORT terminal has begun in the Ust-Luga seaport. Holding company "Novotrans", JSC "Ust-Luga Company" and SU GT Morstroy has started construction of vertical structures.

July
2019

Rosmorrechflot issued a permit for the construction of artificial land plots of the LUGAPORT complex

July
2019

Novotrans received a positive conclusion from the FAA "Glavgosexpertiza of Russia" on the project of creating artificial land plots of the LUGAPORT complex

July
2019

The first stage of delivery of metal structures within the framework of the LUGAPORT investment project has been completed. Lots of 3.6 thousand tons of Larsen sheet metal produced by EVRAZ NTMK and 12 thousand tons of pipes produced by Kolpinsky pipe plant were delivered to the port warehouse site of the General contractor for construction of SU GT Morstroy.

June
2019

On 03.06.2019, the government of the Russian Federation issued order No. 1184-R on the inclusion of the terminal in the territorial planning Scheme for Federal transport (rail, air, sea, inland water transport) and Federal highways

May
2019

The Main technical solutions of the universal trading terminal "Ust-Luga" have been prepared»

April
2019

Environmental expertise of the design documentation of artificial land plots of the 5th and 6th stages of General cargo Complexes in the Ust-Luga seaport was carried out

April
2019

A contract has been concluded with Russian Railways to provide technical support for connecting the non-public railway track of the terminal to the infrastructure of public railway transport at Luzhskaya station (General Park)

February
2019

The investment project is included in the long-Term development program of Rosmorport»

December
2018

Public hearings of the section "environmental Protection" of the project documentation of artificial land plots of the 5th and 6th stages of General cargo Complexes in the Ust-Luga seaport were held

December
2018

Technical conditions for technological connection of the terminal's electric networks to the electric networks of PJSC Lenenergo were obtained"

December
2018

A contract was signed for engineering surveys and preparation of the terminal's design documentation (the developer is CJSC " GT Morstroy»)

November
2018

Rosmorport Federal state unitary enterprise agreed on a Task for conducting engineering surveys and preparing project documentation for the terminal

November
2018

An Agreement was signed with Rosmorport Federal state unitary enterprise on cooperation in the design of facilities provided for by the Ust-Luga Universal trade terminal project»»

August
2018

A full range of engineering surveys was performed to prepare design documentation for artificial land plots of the 5th and 6th stages of General cargo Complexes in the Ust-Luga seaport

August
2018

The Federal Agency for sea and river transport has approved a Petition (Declaration) on investment intentions in the construction of the Ust-Luga Universal trade terminal»

July
2018

The right to sublease a land plot with an area of 15 hectares has been issued

May
2018

Pre-design studies of the terminal placement on 4-6 queues of General cargo Complexes in the Ust-Luga seaport were performed, with a preliminary assessment of technical and economic indicators

April
2018

Pre-project studies of the non-public road junction have been performed
Novotrans Asset LLC to the Luzhskaya station of the Oktyabrskaya railway (developed by PJSC Lengiprotrans)

April
2018

Received Technical conditions of JSC "Russian Railways" for the design of the junction of non-public railway tracks of the terminal to the public infrastructure at the Luzhskaya station (General Park under construction) of the Oktyabrskaya railway

November
2017

Contracts for the purchase and sale of artificial land plots created in the future for the 5th and 6th stages of General cargo Complexes in the Ust-Luga seaport have been concluded

November
2017

An artificial land plot of the 4th stage of General cargo Complexes in the Ust-Luga seaport was purchased